Outfalls/Intakes
Bull Run Dam 2 Tower Improvements for
City of Portland Bureau of Water Works, Clackamas County, Oregon.
The contract involves upgrading the two water intake towers located
in the Bull Run Reservoir #2. The Bull Run watershed is the principal
source of water for the City of Portland. Services include leading
and producing draft work products that relate to environmental,
biological, regulatory, and permitting issues, and coordinating
communications with the City of Portland Bureau of Water Works,
regulatory and resource agencies, and project stakeholders. Specific
tasks include identifying and evaluating water quality, environmental
and biological, permits and regulatory issues, and coordinating
with the resource and regulatory agencies.
Geren
Island Water Treatment Facility Intake Structure Environmental Permitting
for City of Salem Public Works Department, Stayton, Oregon.
The City of Salems Water Treatment Facility contains three
intake structures located off of the north channel of the North
Santiam River. The middle intake is the only fully compliant intake
and was constructed as a part of the Geren Island Water Treatment
Facility Expansion project in 1997. Due to river hydro-dynamics
during low water conditions, there is a buildup of sediments behind
the fish screens. ES&A prepared, submitted and secured USACE/DSL
joint Section 404/Removal-Fill permits and prepared mitigation plans
for modification of the bank located adjacent to and upstream from
the middle intake. Also, ES&A is coordinating with NOAA Fisheries
regarding 4(d) Limit applications submitted for all of the intake
structures.
Cambridge
Village, Logan and Vermont Hills Pump Stations Decommissioning for
City of Portland Bureau of Environmental Services, Portland, Oregon.
The three pump stations are located in environmental zones adjacent
to either the Fanno Creek waterway or tributaries to Fanno Creek.
Also, one of the pump stations is located within the Fanno Creek
100-year floodplain. ES&A conducted vegetation inventories for
the three pump stations that were proposed for decommissioning in
the Fanno Creek basin. ES&A prepared and submitted City of Portland
Land Use applications and responded to questions until approvals
were obtained.